When do we need to perform a heating system reception?
Who should carry out this control?
What do I need to prepare for our visit
What is the price for this service?
What are the requirements of the EPC heating system reception?
Why ask CertiBru to perform this control instead of your heating contractor?
When do we need to perform a heating system reception?
This operation, which is mandatory, needs to be performed during the installation of a new boiler (for a new installation or replacement of an old installation).
Our ”Conseiller Chauffage PEB” type 1 and type 2 will give you an “attestation de réception” of your heating system according to the EPB regulation.
Who should carry out this control?
In French it is the RIT (responsable des installations technique) which means the person responsible for the technical installation. That is to say, the owner of the boiler, or the co-owners (represented by a property management company) in the case of a common boiler.
If the facility is subject to an environmental permit, then the person or the company which is licensed for this environment permit, who will carry on this responsibility.
What do I need to prepare for our visit:
- The entire system must be complete and must already have functioned.
- The logbook of the installation.
- The installation sizing note.
- The building will be free access to verify the compliance of the system as a whole.
For collective installation, the presence of the contractor who performed the work is recommended.
What is the price for this service?
For a type 1 system: one boiler of less than 100 kW.
Installation type | Price VAT included | Price VAT excluded |
---|---|---|
single family installation or one collective installation | 268,00 euros | 221,49 euros |
For a type 2 system: one boiler greater than 100 kW (100 kW included), or several boilers.
Installation type | Price VAT included | Price VAT excluded |
---|---|---|
one or two boilers with a power of less than 500 kW | 580,00 euros | 479,34 euros |
one or two boilers with a power of less than 1000 kW | 678,00 euros | 560,33 euros |
supplement for 3 or 4 boilers | 169,00 euros | 139,67 euros |
more than 4 boilers, for boiler(s) with a power greater than 1000 kW | contact us | - |
What are the requirements of the EPC heating system reception?
Here is the table of points that are checked during the visit.
number | description | Type 1 system | Type 2 system |
---|---|---|---|
1 | Measuring port on the boiler | yes | yes |
2 | Combustion and flue gas emissions (measured) | yes | yes |
3 | Modulation of the burner | yes | yes |
4 | Chimney draft | yes | yes |
5 | Ventilation of the boiler and chimney | yes | yes |
6 | Sealing: flue and air supply | yes | yes |
7 | Size of the boiler | yes | yes |
8 | Insulation of pipes and accessories | yes | yes |
9 | Partitioning heat and air | yes | yes |
10 | Control and programming | yes | yes |
11 | Logbook | yes | yes |
12 | Counts boiler energy | no | yes |
13 | Electric fans counts | no | yes |
14 | Exhaust air heat recovery | no | yes |
15 | Variation in the flow of fresh air | no | yes |
16 | Energy accounting | no | yes |
Why ask CertiBru to perform this control instead of your heating contractor?
We are 100% independent towards your heating contractor.
By using CertiBru, you are guaranteed of an independent work, always in accordance with the law and in your best interests.